The document outlines the flow chart process for a "SLO" from design check through testing and certification. It involves: 1) Submission of technical reports and documents at various stages to government agencies like PJI-PJIS-SAS, SUCOFINDO, PLN, and DISNAKER-ESDM. 2) Design review including grounding, protection systems, and more requiring submission of technical reports. 3) Testing of main and auxiliary equipment, protection systems, and running tests requiring submission of reports. 4) Upon final testing, submission of the final technical report to ESDM and receipt of an SLO certificate.

Uploaded by

Yusuf Alfathony
Copyright
© © All Rights Reserved
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
46 views

Discription Pji-Pjis-Sas Sucofindo PLN Baristand Disnaker Esdm

The document outlines the flow chart process for a "SLO" from design check through testing and certification. It involves: 1) Submission of technical reports and documents at various stages to government agencies like PJI-PJIS-SAS, SUCOFINDO, PLN, and DISNAKER-ESDM. 2) Design review including grounding, protection systems, and more requiring submission of technical reports. 3) Testing of main and auxiliary equipment, protection systems, and running tests requiring submission of reports. 4) Upon final testing, submission of the final technical report to ESDM and receipt of an SLO certificate.

Uploaded by

Yusuf Alfathony
Copyright
© © All Rights Reserved
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 2

FLOW CHART SLO

DISCRIPTION PJI-PJIS-SAS SUCOFINDO PLN BARISTAND DISNAKER ESDM


Check Design Document :
-Main Equipment drawing
-Single Line 2.Result :
-Main Equipment spec. submission the
1.Submission
-Grounding system drawing technical report to
-Layout drawing Disnaker-ESDM
-Fire fighting drawing
-Equipment layout drawing
-Manual book
Main Technical
-Report of UKL-UPL Equipment report
-Permit certificate
-Main equipment certificate

Design review :
-Grounding Design 1.Submission
-Short circuit level 2.Reult submission
-Electrical protection the technical report
-Mechanical Protection to Disnaker-ESDM
-Metering system 3. result :
(mechanical&electrical) Setting relay Technical
-Setting relay protection submit approval report
(must be approve by P2B)
-Clearance distance
-Crepage distance
1.Result :submission
Review of Data record testing- the report to ESDM
commissioning :
- Main Equipment
-Boiler Aux.
-Steam Turbine Aux
-Generator aux
-Transformer
Technical
-Hidrant testing report
-Grounding resistance
-Fucntion test mechanical &
electrical protection
-UPS system
-Oil transformer analisys
-Test sub system & system

1
FLOW CHART SLO

-Squential interlock
-Protection system data record
-Pneumatic and electrical test data
record
-Running test data record

Test system :
- No load test
- Dummy synchrone test
- Synchonization
- Load test 25%-75%-100% 1.Submissio
- Rejection load test (100%)
- NDC test 72 hours
n the final
- Realibility Run technical SLO
-Performance test
report to
Environmental test : ESDM
-Vibration
-Emision
CERTIFICATE
-WWTP system
-Catodic Protection

Technical Report